In odoo18, How can you link a task to a milestone?

Avatar
Kowsalya

In odoo18, How can you link a task to a milestone?
A. Drag and drop the task into the milestone’s column.

B. Fill in the “Milestone” field on the task form.

C. Schedule a “Reach milestone” activity from the task’s chatter.

D. You link projects to milestones, not tasks


Avatar
Discard
1 Answer
0
Avatar
Kowsalya
Best Answer

Answer: Fill in the “Milestone” field on the task form.
Explanation
1. Open the Project and make sure Milestones are enabled.

2. Create a Milestone in the Milestones tab.

3. Open the Task you want to link.

4. In the task form, select the Milestone in the Milestone field and save